General Status
- Some deviations from the original Gantt chart were noted due to evolving project priorities and opportunities.
- Several activities planned for later phases advanced earlier than expected, while some early planned activities are progressing more slowly.
- Examples
- Significant progress on the alignment problem.
- Bidirectional Translator development remains in early stages.
-
Ongoing and Related Activities
- Integration of related efforts such as:
- RAG4EIC
- Amit’s work on job execution and job log analysis
- Local model deployment and larger-scale model execution on Perlmutter using AID2E allocations
-
Computing Resources Under Investigation
- Option A: Small/medium open-source models
- Option B: Cloud-based solutions
- Cloud-based approaches have shown stronger performance for RAG4EIC tasks.
-
Remaining Reporting Period Activities
- Future activities expected through June–September 2026.
-
Research Artifacts
- Ensure all research artifacts acknowledge federal support.
Action Items
-
Progress Report Google Doc (link)
-
All Institutions
Deadline: May 28, 2026 at 10:00 AM (next technical meeting)
- Add any No-Cost-Extension requests related to Phase II.
- Provide a short summary of contributions to Phases I and II.
- Outline projected Phase II contributions for June–September 2026.
- Add all relevant research artifacts from Phases I and II.